Project Completion

Visitor Parking

Signage August 2019

Signage Fabrication

Swimming Pool Tiling June 2019

Completion of Pool Paving

Water Reticulation Valves May 2019

Installation of Valves

Internal Finishes July 2019

Kitchen Installations

HDPE Water Reticulation April 2019

Water Supply Installations

Cabro July 2019

Installation of External Paving

Swimming Pool August 2019

Final Swimming Pool Installations

Electrical Installations August 2019

Final Electrical Fix

External Works July 2019

Cabro Installations

Internal Finishes August 2019

Balustrade Finishes

Front Porch Lighting July 2019

Installation of External Lighting

Soil Works July 2019

Installation of Soil Mixes

External Works July 2019

Kerb Installations

External Works April 2019

Road Handpacked Hardcore

External Works March 2019

Handpacked Hardcore

External Render March 2019

Acrylic Render Application

Roofing Works 2018

Roofing Package Complete

External Works January 2019

Stormwater Line Installation Complete

Internal Finishes 2018

Wall Skimming Complete

External Works April 2019

Water Feature Waterproofing Complete

External Finishes 2018

Hand Dressed Stone Complete

Internal Finishes 2018

Wall Undercoat Spray Painting and Skimming Complete

External Works 2018

Backfilling and Road Compaction Complete

Borehole Installations 2018

Borehole Drilling Complete

External Works 2018

Road and Services Setting Out

Landscaping 2018

Showhouse Landscape Installations

Solar Installations 2018

Fitting Solar Hot Water Units Complete

Internal Finishes 2018

Tiling Installations Complete